Gallery: Full steam ahead for MeyGen installation


Photo courtesy of Atlantis Resources


Atlantis Resources is making final preparations to install the first phase of the MeyGen tidal array project in the Pentland Firth, off Caithness.

Edinburgh-based tidal energy developer has informed that the multiple turbines for the Phase 1A of the MeyGen project are in the final stages of assembly.

Meanwhile, the loadout of the equipment continues at Nigg Energy Park. MeyGen Phase 1A will see the installation of four 1.5MW turbines.

The companies that will conduct the installation at MeyGen project site are DEME Group’s GeoSea working alongside James Fisher Marine Services.

Geosea will use the jack-up vessel MV Neptune to mobilize the equipment and install all heavy turbine foundation structures.

Share this article

Follow Tidal Energy Today

Events>

<< Apr 2017 >>
MTWTFSS
27 28 29 30 31 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30

Offshore Energy 2017

Offshore Energy Exhibition & Conference (OEEC) is Europe’s leading offshore energy event. It is unique in bringing together the oil & gas…

read more >

Waterpower week

The event highlights perspectives on the role of hydro, explores issues affecting hydro and marine resources, and helps participants develop…

read more >

All-Energy Exhibition and Conference 2017

All-Energy has provided the industry suppliers, experts and thought-leaders from the renewable energy supply chain the opportunity…

read more >

The Future of our Seas

At the heart of European Maritime Day is the a 2-day conference “The Future of our Seas”. High-level sessions and stakeholder workshops..

read more >